Govt. of Madhya Pradesh
 
 
Water Supply
       

  

Water Supply

The details of existing water supply system are as under :-
 

S#
Type of items
Quantity
1
T.Ws with pump chamber
420 Nos
2
Underground Tanks
22 Nos
3
Over Head Service Reservoir (OHSR)
15 Nos
4
Water Supply Pipeline
910 Kms
5
Ranney Wells
2 Nos

Augmentation of water supply with the provision of Ranney Well Phase- II. About Rs. 15.22 crore are required for replacement of old lines. The colonies which have been approved by Govt. but there is scarcity water supply. These colonies require for provision of water supply.
 

Demand Chart

Total demand = 13 x 45 Gallon/ Capita / Day = 58.5 MGD

S#
Type of items
MLD
MGD
1
 For Domestic
266 MLD
or 58.5 MGD
2
 For Industrial
20 MLD
or 4.41 MGD
3
 For Commercial
10 MLD
or 2.20 MGD
4
 For Institutional
34 MLD
or 7.49 MGD
6
 For Stand Post
30 MLD
or 6.61 MGD
7
 For Parks
27 MLD
or 5.95 MGD
     Total
387 MLD
85.16 MGD



Installed Capacity
 

S#
Type of items
MLD
MGD
1
 From Tubewells
195 MLD
or 42.95 MGD
2
from Ranney Well
45 MLD
or 10 MGD
     Total
240 MLD
52.95 MGD


Municipal Council Kolar  is trying to bridge the gap between installed capacity and demand by augmenting the infrastructure.